Official notices of work being carried out across Mohawk College on behalf of Facility Services. The information shared here is intended to keep students, employees, and visitors informed about scheduled maintenance, repairs, and construction activities that may impact campus spaces, access, or services.
This Week's Work
Fennell Campus (FF)
A130 – Human Care Lift Installation – MAR 12 – 3:00 PM to 5:00PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Thursday, March 12th, 2026 – 3:00 PM to 5:00PM
Contractor: C&DC Orthomobility
Location: Fennell Campus – A130 Accessible Washroom
Description of Work: Contractors will be installing a new mobility lift in Washroom A130 on Thursday, March 12th.
This work is being completed between 3:00 PM and 5:00 PM, during this time, the washroom will be unavailable.
The nearest accessible washroom is E102.

Figure 1: Fennell Campus - Human Care Lift
For more information please contact:
Paul Dalgleish – Manager, Buildings, Grounds and Housekeeping Operations
Email: paul.dalgleish [at] mohawkcollege.ca (paul[dot]dalgleish[at]mohawkcollege[dot]ca)
B103 & B105 – Gas Monitoring Equipment Installation – MAR 11 & MAR 12 – 8:00 AM to 6:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
- Wednesday, March 11th, 2026 – 8:00 AM to 6:00 PM
- Thursday, March 12th, 2026 – 8:00 AM to 6:00 PM
Contractor: Logixx Security
Location: Fennell Campus
- B103
- B105
Description of Work: Logixx will be installing gas monitoring equipment.
For further information – please contact:
Patrick Belina – Project Manager – Construction and Renovations
Email: patrick.belina [at] mohawkcollege.ca (patrick[dot]belina[at]mohawkcollege[dot]ca)
B103G – Storage/Electrical Room Renovation – MAR 10 – 6:00 AM to 3:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Tuesday, March 10th, 2026 – 6:00 AM to 3:00 PM
Contractor: Britt Drywall
Location: Fennell Campus
- B-Wing 1st Floor: B103G
Description of Work: The contractor will be installing baseboard and chain link fencing. The noisy work will be completed between 6:00 AM to 8:00 AM before classes start.

Figure 1: Fennell Campus – B-Wing B103g
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
C-Wing, F-Wing & J-Wing – AODA Tactile Warning Floor Inserts – MAR 14 & MAR 15 – 9:00 AM to 5:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Saturday, March 14th, 2026 – 9:00 AM to 5:00 PM
Sunday, March 15th, 2026 – 7:00 AM to 5:00 PM
Contractor: Mario’s Tile and Interiors
Location: Fennell Campus
- C-Wing – Stair I leading to the 2nd floor
- F-Wing – near F145 and F146
- J-Wing – Stair E all levels
Description of Work: The contractor will be installing AODA tactile warning floor inserts at the top of the stairs.

Figure 1: Fennell Campus - C-Wing Stair I

Figure 2: Fennell Campus - F-Wing Stair

Figure 3: Fennell Campus - J-Wing Stair E
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
E303 – Corridor Hoarding & Asbestos Remediation – FEB 05 to MAY 29
Facility Services is providing an updated notice of work scheduled to occur in E‑Wing, 3rd Floor, at the Fennell Campus.
Tuesday, January 27th, 2026 to Friday, May 29th, 2026
Note: The information below is a placeholder and will be updated as the project progresses. Future updates will be issued as two‑week look‑ahead schedules become available.
Work Schedule:
- Thursday, February 5th,2026 to Friday, May 29th, 2026 (evening work in Lab E203 to support E303 Lab work)
- Thursday, February 12th, 2026 - Early morning gas service shut down to the second and third floor of E-Wing. Shut down will be performed from 6:00 AM to 7:00 AM. If any dept. has issues with a gas appliance after this work is completed, please reach out to me and I will have our contractors assist in re-lighting your equipment. Thank you for your understanding
Contractor:
General Contractors: Ritestart (Key Holder)
Sub Contractors:
- Mic Mechanical (HVAC)
- Jen-Tech (Electrical)
- Site-Pro (Demolition / Asbestos)
Location: Fennell Campus: E-Wing – Room E303
Description of Work: The contractor will be installing corridor hoarding to protect staff and students from the construction area. There will also be asbestos testing and remediation in the space.
Contractors have received schedules for neighboring classrooms and have been instructed that all disruptive or noisy work must be completed during evening hours and coordinated around the schedules of classrooms E203, E304, and E305.
For further information – please contact:
Tom Ziemkiewicz – Project Manager, Engineering Services
Email: thomas.ziemkiewicz1 [at] mohawkcollege.ca (thomas[dot]ziemkiewicz1[at]mohawkcollege[dot]ca)
E022 and E026 – Washroom Improvements – MAR 09 to MAR 13 – 6:00 AM to 3:00 PM
Facility Services is providing an updated notice of work that will be occurring at the Fennell Campus:
Monday, March 9th, 2026 to Friday, March 13th, 2026 – 6:00 AM to 3:00 PM
Contractor: Britt Drywall
Location: Fennell Campus – Affected Washrooms
E022 – Women’s Washroom
E026 – Men’s Washroom
Description of Work: The contractor be installing new ceilings, replacing toilet partitions, installing urinal screens, door hardware, grab bars, etc.
The washrooms will be out of service as they work on each one. Please use alternate washrooms. They are starting early each day to complete the noisy work before classes.
We apologize for any inconvenience this may cause and appreciate your understanding.

Figure 1: Fennell Campus - E-Wing Level 0 Washrooms
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
E-Wing 1st Floor – Ceiling Cloud Painting – MAR 11 – 4:00 PM to 11:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Wednesday, March 11th, 2026 – 4:00 PM to 11:00 PM
Contractor: RV Painting
Location: Fennell Campus: E-Wing 1st Floor Corridor (across from the elevator)
Description of Work: The contractor will be patching and painting the drywall ceiling clouds in the E-Wing, 1st Floor corridor across from the elevator.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
F118 – Seating Removal – MAR 09 – 7:00 AM to 6:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Monday, March 9th, 2026 – 7:00 AM to 6:00 PM
Contractor: Britt Drywall
Location: Fennell Campus – Room F118
Description of Work: Removal of the fixed swing arm chairs.
For further information – please contact:
Sloan Alessandro – Project Manager, Construction Engineering Services
Email: sloan.alessandro [at] mohawkcollege.ca (sloan[dot]alessandro[at]mohawkcollege[dot]ca)
EA211 – Electrical Work – MAR 13 – 11:00 AM to 2:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Friday, March 13th, 2026 – 11:00 AM to 2:00 PM
Contractor: LJ Barton
Location: Fennell Campus – Room EA211
Description of work: LJ Barton will be turning off the electrical panel in EA211 tomorrow between 11:00 AM and 2:00 PM.
This will only impact EA211 and receptacles in EA210A. No other areas will be impacted.
For more information please contact:
Paul Dalgleish – Manager, Buildings, Grounds and Housekeeping Operations
Email: paul.dalgleish [at] mohawkcollege.ca (paul[dot]dalgleish[at]mohawkcollege[dot]ca)
J-Wing – Exterior Sign Installation – MAR 12 – 8:00 AM to 4:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
- Thursday, March 12th, 2026 – 8:00 AM to 4:00 PM
Contractor: RM Signs
Location: Fennell Campus (exterior building, photo attached for reference)
Description of Work: The contractor will be installing a large flex face sign on the exterior building outside of J-Wing.

Figure 1: Fennell Campus - Exterior Location of Work
For further information – please contact:
Lindsay Nero – Manager, Brand Engagement
Email: lindsay.nero [at] mohawkcollege.ca (lindsay[dot]nero[at]mohawkcollege[dot]ca)
J-Wing 1st Floor – Building Services Investigation – MAR 17 & MAR 18 – 7:00 AM - 5:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Tuesday, March 17th, 2026 & Wednesday, March 18th, 2026 – 7:00 AM - 5:00 PM
Contractor: Britt Drywall
Location: Fennell Campus – J-Wing Rooms ( J104, J106, J106A, J106B, J108, J110, J114)
Description of Work: The contractor will be completing some investigative work to determine the location of any services that are buried withing the perimeter of the rooms listed above.
The washrooms in this area will be closed for the duration of the work.
Alternatively, the washrooms on the floor above and below level one will be available for use.
For further information – please contact:
Domenic Grandoni – Engineering Services Officer
Email: domenic.grandoni1 [at] mohawkcollege.ca (domenic[dot]grandoni1[at]mohawkcollege[dot]ca)
Stoney Creek Campus (SC)
A, B, C, D, G Wings & Exterior – Electrical Shutdown Campus wide – MAR 11 & MAR 12 – 10:00 PM to 6:00 AM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
- Wednesday, March 11th, 2026 @ 10:00 PM to Thursday March 12th @ 6:00 AM
- Thursday, March 12th, 2026 @ 10:00 PM to Friday March 13th @ 6:00 AM
Contractor: Cahill Electric Ltd
Location: Stoney Creek Campus, A/B/C/D/G Wings and Exterior
Description of Work: All building power will be off for the duration of these shutdowns. The Generator will be operating to maintain some aspects of IT, Security and Lighting. Elevators will not be operating.
Any computers and other office equipment that can be turned off at the end of the day on Wednesday and Thursday would be prudent and appreciated.
For further information – please contact:
Jim Davidson – Project Manager – Construction and Electrical
Email: james.davidson10 [at] mohawkcollege.ca (james[dot]davidson10[at]mohawkcollege[dot]ca)
A, B, C, D, F and G-Wings – Painting – MAR 09 – 4:00 PM to 11:00 PM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Monday, March 9th, 2026 – 4:00 PM to 11:00 PM
Contractor: RV Painting
Location: Stoney Creek Campus:
- A-Wing 2nd Floor corridor
- B-Wing corridor
- C-Wing corridor
- D-Wing corridor
- F-Wing corridor
- G-Wing washrooms
Description of Work: The contractor will be painting around newly installed exit signs and conduits.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
B106 – Compressed Air Work – MAR 10 - MAR 13 – 8:00 AM to 5:00 PM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
- Tuesday, March 10th, 2026 – 8:00 AM to 5:00 PM
- Wednesday, March 11th, 2026 – 8:00 AM to 5:00 PM
- Thursday, March 12th, 2026 – 8:00 AM to 5:00 PM
- Friday, March 13th, 2026 – 8:00 AM to 5:00 PM
Contractor: Barton Air Sales and Service
Location: Stoney Creek Campus: Room B106
Description of Work: Compressed air system installation of new equipment. There should be no impact from this work outside of B106.
For further information – please contact:
Patrick Belina – Project Manager – Construction and Renovations
Email: patrick.belina [at] mohawkcollege.ca (patrick[dot]belina[at]mohawkcollege[dot]ca)
C131 – Window Unit Replacements – MAR 13 & MAR 14 – 1:00 PM to 7:00 PM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
- Friday, March 13th, 2026 – 1:00 PM to 7:00 PM
Saturday, March 14th, 2026 – 8:00 AM to 12:00 PM (if required)
Contractor: Alwind Industries
Location: Stoney Creek Campus – Room C131 – Machine Shop
Description of Work: Replacement of fixed window units in C131 Machine Shop with operable window units.
For further information – please contact:
Sloan Alessandro – Project Manager, Construction Engineering Services
Email: sloan.alessandro [at] mohawkcollege.ca (sloan[dot]alessandro[at]mohawkcollege[dot]ca)
E109E – Electrical Room Work – MAR 13 to MAR 15 - until 5:00 PM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Friday, March 13th, 2026 @ 5:00 PM to Sunday, March 15th, 2026 @ 5:00 PM
Contractor: T.Lloyd Electric Ltd.
Location: Stoney Creek Campus: E-Wing Building (Entire Building)
Description of Work: Modifications to the building’s electrical distribution will be taking place over the weekend. As a result, all power to the entire building will be turned off from Friday at 5:00 PM. The work is scheduled to conclude on Sunday at 5:00 PM at which time, the power will be restored.
Note that building will remain closed and locked during this shutdown.
For further information – please contact:
Jim Davidson – Project Manager – Electrical & Construction
Email: james.davidson10 [at] mohawkcollege.ca (james[dot]davidson10[at]mohawkcollege[dot]ca)
E109 – Mechanical and Electrical Work – FEB 25, MAR 04, MAR 11 – 7:00 AM to 5:00 PM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
- Wednesday, February 25th, 2026 – 7:00 AM to 5:00 PM
- Wednesday, March 4th, 2026 – 7:00 AM to 5:00 PM
- Wednesday, March 11th, 2026 – 7:00 AM to 5:00 PM
Contractor: L.J. Barton Mechanical Inc.
Location: Stoney Creek Campus – Room E109
Description of Work: L.J. Barton will complete the following work in E109 on the main floor, the large mezzanine and the roof.
- Remove electrical controls and feeds within the paint booth related to exhaust and MUA unit.
- Remove conduit and junction boxes associated with exhaust and MUA unit back to electrical room.
- Disconnect and cap gas line feeding MUA.
- Disconnect and remove feed to MUA and Exhaust fan on roof.
- Remove branch ducts for small exhaust fan and add round diffuser at fire damper.
Please Note: A scissor lift will be used to complete the work. The work will generate noise.
For health and safety reasons, it is preferred that staff do not access the space on these days.

Figure 1: Stoney Creek - E109 Main Level – Green area indicates place of the work.

Figure 2: Stoney Creek - E109 Mezzanine Level – Green area indicates place of the work.
For further information – please contact:
Natalie Fasan – Manager, Engineering Services & Projects
Email: natalie.fasan [at] mohawkcollege.ca (natalie[dot]fasan[at]mohawkcollege[dot]ca)
E109A – Demolition and Removal – MAR 11 & MAR 12 – 7:00 AM to 5:00 PM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Wednesday, March 11th, 2026 & Thursday, March 12th, 2026 – 7:00 AM to 5:00 PM
Contractor: Torham Construction and Restoration Inc.
Location: Stoney Creek Campus – Room E109A
Description of Work: Demolition and removal of SC - E109A paint booth components, ductwork and related equipment. The demolition materials will be removed through the exit door of E109A facing the parking lot to the north and brought to a waste bin in the parking lot.
The contractor will ensure safe pedestrian walkways and roadways are maintained for the duration of the work when they move materials to the waste bin.
For further information – please contact:
Natalie Fasan – Manager, Engineering Services and Projects
Email: natalie.fasan [at] mohawkcollege.ca (natalie[dot]fasan[at]mohawkcollege[dot]ca)
E-Wing – Electrical Conduit Installation – MAR 09 - MAR 12 – 5:00 PM to 4:00 AM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
- Monday, March 9th, 2026 – 5:00 PM to 4:00 AM
- Tuesday, March 10th, 2026 – 5:00 PM to 4:00 AM
- Wednesday, March 11th, 2026 – 5:00 PM to 4:00 AM
- Thursday, March 12th, 2026 – 5:00 PM to 4:00 AM
**ALL WORK IS SCHEDULED TO AVOID ANY CLASSES IN ANY OF THE SHOPS.
Contractor: O’Keefe Electrical
Location: Stoney Creek Campus - E-Wing (Entire Building)
Description of Work: O’Keefe Electrical will be installing electrical conduit below the ceiling deck though all shops.
For further information – please contact:
Jim Davidson – Project Manager – Electrical & Construction
Email: james.davidson10 [at] mohawkcollege.ca (james[dot]davidson10[at]mohawkcollege[dot]ca)
Institute of Applied Health Sciences (IAHS)
There is no scheduled work during this period.
Centre for Aviation Technology at Hamilton International Airport (HA)
There is no scheduled work during this period.
Upcoming Work
Fennell Campus (FF)
A, B, E, F, G-Wing – Painting Work – MAR 16 – 4:00 PM to 11:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Monday, March 16th, 2026 – 4:00 PM to 11:00 PM
Contractor: RV Painting
Location: Fennell Campus
- A114 (patching holes and re-painting door/frame)
- B102A (touch-up painting around new exit signs)
- E-Wing 2nd and 3rd floors (touch-up painting around new exit signs)
- F-Wing (touch-up painting around new exit signs)
- G010 (patching holes and re-painting door/frame)
Description of Work: The contractor will be patching and painting the areas summarized above.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
B103 & B105 – Gas Detection Equipment Installation – MAR 21 – 7:00 AM to 5:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Updated Schedule:
- Saturday, March 21st, 2026 – 7:00 AM to 5:00 PM
Contractor: O’Keefe Electrical and Lancaster Group
Location: Fennell Campus
- B103
- B105
Description of Work: O’Keefe Electrical and Lancaster Group will be commissioning gas detection equipment in B103 and B105. Please note that the alarms and strobes will go off temporarily during this process to test their operation.
For further information – please contact:
Domenic Grandoni – Engineering Services Officer
Email: domenic.grandoni1 [at] mohawkcollege.ca (domenic[dot]grandoni1[at]mohawkcollege[dot]ca)
EA004 – Universal Washroom AODA Improvement – MAR 16 & MAR 17 – 7:00 AM to 3:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Monday, March 16th, 2026 to Tuesday, March 17th, 2026 from 7:00 AM to 3:00 PM
Contractor: Britt Drywall
Location: Fennell Campus : EA004 – Universal Washroom
Description of Work: The contractor be cutting out the drywall, installing backing, reinstalling the drywall, patching and painting to install a new baby change table.
The washroom will be out of service. Please use alternate washroom.
We apologize for any inconvenience this may cause and appreciate your understanding.

Figure 1: Fennell Campus - EA-Wing Level 0 Washroom EA004
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
C-Wing & F-Wing – Electrical Panel Replacement – MAR 17 – 7:00 AM to 5:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Tuesday, March 17th, 2026 – 7:00 AM to 5:00 PM
Company: Cahill Electric Limited
Location: Fennell Campus: C-Wing & F-Wing
Description of Work: This contractor will be completing an ESA Inspection.
For further information – please contact:
Domenic Grandoni – Engineering Services Officer
Email: domenic.grandoni1 [at] mohawkcollege.ca (domenic[dot]grandoni1[at]mohawkcollege[dot]ca)
J-Wing 1st Floor – Bathrooms Building Services Investigation - MAR 17 & MAR 18 – 7:00 AM - 5:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Monday, March 17th, 2026 – 7:00 AM - 5:00 PM
- Rooms: J104, J106, J106A, J106B, J108, J110 & J114
Tuesday, March 18th, 2026 – 7:00 AM - 5:00PM
- Rooms: J006, J008, & J014
Contractor: Britt Drywall
Location: Fennell Campus: J-Wing Washrooms: J104, J106 ,J106A, J106B, J108, J110, J114, J006, J008 & J014
Description of Work: The contractor will be completing some investigative work to determine the location of any services that are buried within the perimeter of the rooms listed above.
The washrooms in this area will be closed for the duration of the work. Alternatively, the washrooms on the floor above and/or below the washrooms will be available for use.
For further information – please contact:
Domenic Grandoni – Engineering Services Officer
Email: domenic.grandoni1 [at] mohawkcollege.ca (domenic[dot]grandoni1[at]mohawkcollege[dot]ca)
Stoney Creek Campus (SC)
A, D, F and G-Wing – AODA Upgrades and Misc Work – MAR 18 - MAR 20 – 7:00 AM to 3:00 PM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Wednesday, March 18th, 2026 to Friday, March 20th, 2026 – 7:00 AM to 3:00 PM
Contractor: Britt Drywall
Location: Stoney Creek Campus
- A125A – Women’s Change Room
- A125B – Men’s Change Room
- A133 – Universal Washroom
- D-Wing – Corridor at Exit #26 and #27
- F-Wing – Exit #1 Vestibule
- G106 – Universal Washroom
- G112 – Men’s Washroom
Description of Work: The contractor will install AODA-compliant washroom accessories, increase the door undercut at the F-Wing Exit #1 inner vestibule door, and complete drywall patching and painting at Exits #26 and #27.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
B106 – Compressed Air Work – MAR 16 to MAR 20 – 8:00 AM to 5:00 PM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
- Monday, March 16th, 2026 – 8:00 AM to 5:00 PM
- Tuesday, March 17th, 2026 – 8:00 AM to 5:00 PM
- Tuesday, March 17th, 2026 – 10:00 PM to 6:00 AM (AFTER-HOURS FOR TIE INS)
- Wednesday, March 18th, 2026 – 8:00 AM to 5:00 PM
- Thursday, March 19th, 2026 – 8:00 AM to 5:00 PM
- Friday, March 20th, 2026 – 8:00 AM to 5:00 PM
Contractor: Barton Air Sales and Service
Location: Stoney Creek Campus: Room B106
Description of Work: Compressed air system installation of new equipment. There should be no impact from this work outside of B106 other than for the tie-in which will occur after-hours.
For further information – please contact:
Jim Davidson – Project Manager – Electrical & Construction
Email: james.davidson10 [at] mohawkcollege.ca (james[dot]davidson10[at]mohawkcollege[dot]ca)
D-Wing – Corridor Wiring Clean-up – MAR 16 – 4:00 PM to 12:00 AM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Monday, March 16th, 2026 – 4:00 PM to 12:00 AM
(Security: They are only estimating the end time, please allow them to continue until they have completed their work)
Contractor: O’Keefe Electrical
Location: Stoney Creek Campus: D-Wing corridor between D102 and D112
Description of Work: The contractor will be cleaning up the last remaining wiring and relocating a clock. The majority of the wiring will be the assistance phones in the corridors and redundant PA system wiring, so there will be alarms to security as they work on each assistance phone location to re-route the wiring.

Figure 1: Stoney Creek Campus – D-Wing Corridor
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
E109 – Carpentry Shop Washrooms – MAR 18 – 7:00 AM to 12:30 PM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Wednesday, March 18th, 2026 – 7:00 AM to 12:30 PM
Contractor: Britt Drywall
Location: Stoney Creek Campus: E-Wing – E109 Carpentry Shop Washrooms
Description of Work: The contractor will be installing door closers, kickplates, push plates, lever handles, hinges and painting the doors and frames.
Please use alternate washrooms during this time.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
Institute of Applied Health Sciences (IAHS)
There is no scheduled work during this period.
Centre for Aviation Technology at Hamilton International Airport (HA)
There is no scheduled work during this period.
Archived Notices
Fennell Campus (FF)
All Elevators - Scheduled Elevator Emergency Phone Line Updates – MAR 05 – 8:30 AM to 4:30 PM
Facility Services is providing notice of work that will be occurring at the Fennell and Stoney Creek Campus:
Thursday, March 5th, 2026 – 8:30 AM to 4:30 PM
Contractor: Schindler Elevator Corporation
Location: Fennell & Stoney Creek Campus - Elevators
Description of Work: Schindler Elevator technicians will be on site to reprogram the emergency phone lines for all elevators at the Fennell and Stoney Creek Campus. Each elevator will be taken out of service for up to one hour while its phone line is updated to the new emergency contact number.
Teams will work in sequence, with two crews on site to complete all elevators in one day. During this time, the elevator undergoing work will be temporarily unavailable; however, Schindler can provide access if required for students or staff. After reprogramming, each elevator will be functionally tested to ensure correct operation and call routing.
For more information please contact:
Paul Dalgleish – Manager, Buildings, Grounds and Housekeeping Operations
Email: paul.dalgleish [at] mohawkcollege.ca (paul[dot]dalgleish[at]mohawkcollege[dot]ca)
E022 & E026 – Washroom Improvements – FEB 27 to MAR 06 – 6:00 AM to 3:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Friday, February 27th, 2026 to Friday, March 6th, 2026 – 6:00 AM to 3:00 PM
Contractor: Britt Drywall
Location: Fennell Campus – Affected Washrooms
E022 – Women’s Washroom
E026 – Men’s Washroom
Description of Work: The contractor be installing new ceilings, replacing toilet partitions, installing urinal screens, door hardware, grab bars, etc.
The washrooms will be out of service as they work on each one. Please use alternate washrooms. They are starting early each day to complete the noisy work before classes.
We apologize for any inconvenience this may cause and appreciate your understanding.

Figure 1: Fennell Campus - E-Wing Level 0 Washrooms
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
B-Wing – Gas Detection Equipment Installation – MAR 02 to MAR 07 – 11:00 AM to 10:00 PM - *UPDATED
Facility Services is providing an updated notice of work that will be occurring at the Fennell Campus:
Updated Schedule:
- Friday, March 6th, 2026 – 11:00 AM to 10:00 PM
- Saturday, March 7th, 2026 – 7:00 AM to 5:00PM
Original Schedule:
Monday, March 2nd, 2026 – 10:00 PM to 6:00 AM
Tuesday, March 3rd, 2026 – 10:00 PM to 6:00 AM
Wednesday, March 4th, 2026 – 5:00 PM to 6:00 AM
Thursday, March 5th, 2026 – 10:00 PM to 6:00 AM
Contractor: O’Keefe Electrical
Location: Fennell Campus
- B103
- B105
Description of Work: O’Keefe Electrical will be installing gas detection equipment.
For further information – please contact:
Patrick Belina – Project Manager – Construction and Renovations
Email: patrick.belina [at] mohawkcollege.ca (patrick[dot]belina[at]mohawkcollege[dot]ca)
C-Wing – Tim Hortons Express Hot Water Heater Upgrade – MAR 05 – 5:00 PM to 10:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Thursday, March 5th, 2026 – 5:00 PM to 10:00 PM
Contractor: LJ Barton
Location: Fennell Campus: C-Wing - Tim Hortons Express
Description of Work: LJ Barton will be upgrading the hot water heater for the Tim Hortons Express.
No impact to the operation of the College, all work will be contained in the Tim Hortons space.
For more information please contact:
Paul Dalgleish – Manager, Buildings, Grounds and Housekeeping Operations
Email: paul.dalgleish [at] mohawkcollege.ca (paul[dot]dalgleish[at]mohawkcollege[dot]ca)
E-Wing & F-Wing – Exit Light Replacements – MAR 03 & MAR 05 – 6:00 PM to 11:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Tuesday, March 3rd, 2026 and Thursday, March 5th, 2026 – 6:00 PM to 11:00 PM
Contractor: O’Keefe Electrical
Location: Fennell Campus
- E-Wing 2nd and 3rd Floor Corridors
- F-Wing Basement and 1st Floor Corridors
Description of Work: O’Keefe Electrical will be replacing existing exit lights with new ones and installing some in new locations.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
E-Wing – Exit Lights Installation – MAR 06 – 7:00 AM to 1:00 PM
Facility Services is providing an updated notice of work that will be occurring at the Fennell Campus:
Friday, March 6th, 2026 – 7:00 AM to 1:00 PM
Contractor: O’Keefe Electrical
Location: Fennell Campus: E-Wing 2nd and 3rd Floor Corridors
Description of Work: O’Keefe Electrical will be installing two new exit signs.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
F-Wing – Exit Light Replacements – MAR 02 – 6:00 PM to 11:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Monday, March 2nd, 2026 – 6:00 PM to 11:00 PM
Contractor: O’Keefe Electrical
Location: Fennell Campus: F-Wing Basement and 1st Floor Corridors and F108
Description of Work: O’Keefe Electrical will be replacing existing exit lights with new ones and installing some in new locations.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
F114 & E-Wing 1st Floor Ceiling Cloud – Painting – MAR 07 – 6:00 AM to 3:00 PM - *UPDATED
Facility Services is providing an updated notice of work that will be occurring at the Fennell Campus:
Updated Schedule: Saturday, March 7th, 2026 – 6:00 AM to 3:00 PM
Original Schedule: Tuesday, March 3rd, 2026 – 4:30 PM to 11:00 PM
Contractor: RV Painting
Location: Fennell Campus: Room F114 & E-Wing 1st Floor Corridor
Description of Work: The contractor will complete painting touch-ups in Room F114 where signage was removed and will paint the drywall ceiling clouds in the E-Wing, 1st Floor corridor.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
G109y and G109z – Washrooms Duress System – MAR 02 – 8:00 AM to 5:00 PM
Facility Services is providing an updated notice of work that will be occurring at the Fennell Campus:
Monday, March 2nd, 2026 – 8:00 AM to 5:00 PM
Contractor: O’Keefe Electrical
Location: Fennell Campus
- G109y Universal Washroom
- G109z Universal Washroom
Description of Work: O’Keefe Electrical will be upgrading/installing a Duress System in each washroom. The washrooms will be out of order during this time.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
E-Wing – Window Replacement – DEC 15 to FEB 28
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Monday, December 15th, 2025 – Saturday, February 28th, 2025 from 7:00 AM – 7:00 PM
Contractor: Alwind Industries Ltd.
Location: Fennell Campus: E-Wing South Elevation
Description of Work: The existing windows of the E-Wing’s south elevation will be replaced. Work will be scheduled per room to minimize disruption to students and staff.
These rooms are included in the replacement project.
- Level 00 – E003, E005, E009, E011, E027, E031, E033
- Level 01 – E103, E105, E107, E109, E111, E113, E121, E123, E125
- Level 02 – E203, E205, E209, E227, E229, E229b, E229f, E231, E233
- Level 03 – E303, E305, E307, E309, E327, E329, E331

Figure 1: Blue dotted line denotes the area of work (E-Wing South Elevation)

Figure 2: Overview of the area of work (E-Wing South Elevation) All existing windows are scheduled to be replaced.

Figure 3: Overview of the staging areas: Blue – Disposal Bin, Orange – Fenced Staging Area (Storage Trailer, Boom Lift, etc.) All current refuse containers (red arrows) will remain accessible throughout the project, along with access to the MPAC loading dock.
For further information – please contact:
Sloan Alessandro – Project Manager, Construction Engineering Services
Email: sloan.alessandro [at] mohawkcollege.ca (sloan[dot]alessandro[at]mohawkcollege[dot]ca)
E-Wing – Window Covering Installation – FEB 17 to FEB 27
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Tuesday, February 17th, 2026 to Friday, February 27th, 2026 – 7:00 AM to 5:00 PM
Contractor: Elite Pro Shading Systems / Tri City Blinds
Location: Fennell Campus – E-Wing
Description of Work: Installation of new roller‑shade window coverings. Work will be scheduled around active classrooms and will take place only in rooms on Levels 00, 02, and 03 where roller shades are not currently installed and where new windows have already been completed.
For further information – please contact:
Sloan Alessandro – Project Manager, Construction Engineering Services
Email: sloan.alessandro [at] mohawkcollege.ca (sloan[dot]alessandro[at]mohawkcollege[dot]ca)
E116 & E118 – Washroom Improvements – FEB 23 to FEB 27
Facility Services is providing an updated notice of work that will be occurring at the Fennell Campus:
Monday, February 23rd, 2026 to Friday, February 27th, 2026 – 6:00 AM to 3:00 PM
Contractor: Britt Drywall
Location: Fennell Campus – Affected Washrooms
E116 – Women’s Washroom
E118 – Men’s Washroom
Description of Work: The contractor be installing new ceilings, replacing toilet partitions, installing urinal screens, door hardware, grab bars, etc.
The washrooms will be out of service as they work on each one. Please use alternate washrooms. They are starting early each day to complete the noisy work before classes.
We apologize for any inconvenience this may cause and appreciate your understanding.

Figure 1: Fennell Campus - E-Wing Level 1 Washrooms
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
C-Wing & E-Wing – Sanitary Pits Cleaning – FEB 27
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Friday, February 27th, 2026 – 7:00 AM to 5:00 PM
Contractor: W.M. Groves
Location: Fennell Campus – Campus Wide
Description of Work: W.M. Groves will be on site on Friday, February 27th at 7:00 AM to perform the cleaning of sanitary pits across Campus. This includes C002, C039, C079, and E030d. The contractors will be parked outside with hoses running in the building.
There will be some slight odours in the immediate areas of the cleaning, but will dissipate throughout the day.
For more information please contact:
Paul Dalgleish – Manager, Buildings, Grounds and Housekeeping Operations
Email: paul.dalgleish [at] mohawkcollege.ca (paul[dot]dalgleish[at]mohawkcollege[dot]ca)
F114 – Corridor Painting – FEB 23 to FEB 25
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Monday, February 23rd, 2026 to Wednesday, February 25th, 2026 – 4:30 PM to 11:00 PM
Contractor: RV Painting
Location: Fennell Campus: Room F114 (Corridor)
Description of Work: The contractor will be painting the corridor walls around F114.

Figure 1: Fennell Campus – F-Wing F114
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
G109y and G109z – Washrooms Duress System – FEB 23
Facility Services is providing an updated notice of work that will be occurring at the Fennell Campus:
Updated Schedule: Monday, February 23rd, 2026 – 8:00 AM to 5:00 PM
Contractor: O’Keefe Electrical
Location: Fennell Campus
- G109y Universal Washroom
- G109z Universal Washroom
Description of Work: O’Keefe Electrical will be upgrading/installing a Duress System in each washroom. The washrooms will be out of order during this time.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
Campus Wide – Sanitary Pits Cleaning – FEB 27
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Friday, February 27th, 2026 – 7:00 AM to 5:00 PM
Contractor: W.M. Groves
Location: Fennell Campus – Campus Wide
Description of Work: W.M. Groves will be on site on Friday, February 27th at 7:00 AM to perform the cleaning of sanitary pits across Campus. This includes C002, C039, C079, and E030d. The contractors will be parked outside with hoses running in the building.
There will be some slight odours in the immediate areas of the cleaning, but will dissipate throughout the day.
For more information please contact:
Paul Dalgleish – Manager, Buildings, Grounds and Housekeeping Operations
Email: paul.dalgleish [at] mohawkcollege.ca (paul[dot]dalgleish[at]mohawkcollege[dot]ca)
B103 & B105 – Gas Detection Equipment Installation – FEB 16, FEB 17, FEB 19
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Monday, February 16th, 2026 – 6:00 AM to 10:00 PM
Tuesday, February 17th, 2026 – 6:00 AM to 10:00 PM
Thursday, February 19th, 2026 – 6:00 AM to 10:00 PM
Contractor: O’Keefe Electrical
Location: Fennell Campus - Rooms B103 & B105
Description of Work: O’Keefe Electrical will be installing gas detection equipment.
For further information – please contact:
Patrick Belina – Project Manager – Construction and Renovations
Email: patrick.belina [at] mohawkcollege.ca (patrick[dot]belina[at]mohawkcollege[dot]ca)
B, C, E & F-Wing – Exit Light Replacements – FEB 16, FEB 18, FEB 20
Facility Services is providing an updated notice of work that will be occurring at the Fennell Campus:
Revised Schedule: Wednesday, February 18th, 2026 and Friday, February 20th, 2026 – 8:00 AM to 5:00 PM
Original Schedule: Monday, February 16th, 2026 – 6:00 AM to 6:00 PM
Contractor: O’Keefe Electrical
Location: Fennell Campus
- B102, B103, B104 and B105
- C041
- E-Wing 2nd and 3rd Floor Corridors
- F-Wing Basement and 1st Floor Corridors, F108 and F118
Description of Work: O’Keefe Electrical will be replacing existing exit lights with new ones and installing some in new locations.
All breakers impacted are labelled as Exit Lights.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
C109 – Health & Wellness Centre Painting – FEB 17
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Tuesday, February 17th, 2026 – 8:00 AM to 4:00 PM
Contractor: RV Painting
Location: Fennell Campus: Room C109
Description of Work: The contractor will be painting a feature wall behind the reception desk.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
C, G, & I-Wing – AODA Tactile Warning Plates – FEB 17 & FEB 18
Facility Services is providing an updated notice of work for that will be occurring at the Fennell Campus:
Revised Schedule: Wednesday, February 18th, 2026 – 8:00 AM to 4:00 PM
Original Schedule: Tuesday, February 17th, 2026 – 8:00 AM to 4:00 PM
Contractor: Bestco Construction
Location: Fennell Campus
- C-Wing – Stair I (remaining area to be completed)
- C-Wing – Stair H (completed)
- G-Wing – Cellar Stair (completed)
- i-Wing – Stair P (completed)
Description of Work: The contractor will be installing AODA tactile warning plates at the top of the stairs.

Figure 1: Fennell Campus – C-Wing Stair I
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
C-Wing and F-Wing – Final Panel Touch Ups – FEB 21
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Saturday, February 21st, 2026 – 8:00 AM to 5:00 PM
Contractor: RV Painting
Location: Fennell Campus
- C102
- C202
- F102i
- F-Wing Corridor near F143
Description of Work: The contractor will be touching up the paint on the electrical panels in the above rooms in C-Wing and F-Wing
For further information – please contact:
Patrick Belina – Project Manager – Construction and Renovations
Email: patrick.belina [at] mohawkcollege.ca (patrick[dot]belina[at]mohawkcollege[dot]ca)
E116 & E118 – Washroom Improvements – FEB 17 to FEB 20
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Tuesday, February 17th, 2026 to Friday, February 20th, 2026 from 7:00 AM to 5:00 PM
Schedule for the following week is to be determined and will be shared when available.
Contractor: Britt Drywall
Location: Fennell Campus – Affected Washrooms
E116 – Women’s Washroom
E118 – Men’s Washroom
Description of Work: The contractor be installing new ceilings, replacing toilet partitions, installing urinal screens, door hardware, grab bars, etc… The washrooms will be out of service as they work on each one. Please use alternate washrooms. This work will be noisy at times.
We apologize for any inconvenience this may cause and appreciate your understanding.

Figure 1: Fennell Campus - E-Wing Level 1 Washrooms
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
EA-Wing – JCPI - HVAC Maintenance – FEB 17 to FEB 20
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Reading Week: Tuesday, February 17th, 2026 to Friday, February 20th, 2026 – 7:00 AM to 4:00 PM
Contractor: Daikin Applied
Location: Fennell Campus: EA‑Wing (Joyce Centre for Partnership and Innovation — JCPI)
Description of Work: Contractors will be on site throughout Reading Week to complete maintenance and servicing of the HVAC equipment across all four floors of the JCPI.
This work will involve technicians accessing labs, classrooms, and theatres as needed to reach the equipment.
Please advise if you have any large events, exams, or reason that your space can not be accessed, and we will work around any scheduled events or bookings.
For more information please contact:
Paul Dalgleish – Manager, Buildings, Grounds and Housekeeping Operations
Email: paul.dalgleish [at] mohawkcollege.ca (paul[dot]dalgleish[at]mohawkcollege[dot]ca)
F-Wing – F144, F146, F148 – Roof Top Unit Replacement – FEB 17 to FEB 20
Facility Services is providing a notice of work scheduled to occur in F‑Wing, F144-F148, at the Fennell Campus.
Tuesday, February 17th, 2026 to Friday, February 20th, 2026
Contractors:
- General Contractors: VanAm Mechanical (Key Holder)
- Sub Contractors: Southern Ontario Electric (Electrical)
Location: Fennell Campus: F-Wing – Rooms F144, F146, F148 and associated corridors.
Description of Work: The contractor will be removing and replacing aged root top equipment with new more efficient equipment.

Figure 1: Fennell Campus - F-Wing – F144 / F148 Area
For further information – please contact:
Tom Ziemkiewicz – Project Manager, Engineering Services
Email: thomas.ziemkiewicz1 [at] mohawkcollege.ca (thomas[dot]ziemkiewicz1[at]mohawkcollege[dot]ca)
G109y and G109z – Washrooms Duress System – FEB 18 & FEB 20
Facility Services is providing an updated notice of work that will be occurring at the Fennell Campus:
Revised Schedule: Friday, February 20th, 2026 – 8:00 AM to 5:00 PM
Original Schedule: Wednesday, February 18th, 2026 – 8:00 AM to 5:00 PM
Contractor: O’Keefe Electrical
Location: Fennell Campus
- G109y Universal Washroom
- G109z Universal Washroom
Description of Work: O’Keefe Electrical will be upgrading/installing a Duress System in each washroom. The washrooms will be out of order during this time.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
Work Mobile: 905-961-1465
M-Wing – Road Closure and Crane for HVAC Unit Install – FEB 17
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Tuesday, February 17th, 2026 – 6:00 AM to 5:00 PM
Contractor: Modern Niagara
Location: Fennell Campus – M-Wing
Description of Work: Modern Niagara will be on site on Tuesday, February 17th, 2026 to install a new HVAC unit on the roof of M-Wing. There will be a crane on site parked on the maintenance road leading from Governor’s Blvd to E-Wing from 6:00 AM to 2:00 PM, restricting use of this road. The building (M-Wing) will be restricted from access for the day, but will be accessible the morning of Wednesday, February 18th, 2026 and moving forward.
We appreciate your patience with this project.

Figure 1: Fennell Campus - Road Closure - Governor's Blvd to E-Wing Maintenance Road
For more information please contact:
Paul Dalgleish – Manager, Buildings, Grounds and Housekeeping Operations
Email: paul.dalgleish [at] mohawkcollege.ca (paul[dot]dalgleish[at]mohawkcollege[dot]ca)
B103G – Storage/Electrical Room Renovation – FEB 10 & FEB 11
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Tuesday, February 10th, 2026 to Wednesday, February 11th, 2026 from 6:00 AM to 3:00 PM
Contractor: Britt Drywall
Location: Fennell Campus: B-Wing 1st Floor: B103G
Description of Work: The contractor will be removing a drywall partition and installing a chain link fence separating the storage room from the electrical panels. Miscellaneous electrical/lighting work along with painting and baseboard.
The noisy work will be completed between 6:00 AM to 8:00 AM.

Figure 1: Fennell Campus – B-Wing B103g
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
B103G – Storage/Electrical Room Renovation – FEB 12
Facility Services is providing an updated notice of work that will be occurring at the Fennell Campus:
Thursday, February 12th, 2026 from 7:00 AM to 3:00 PM
Contractor: Britt Drywall and their sub-contractor O’Keefe Electrical
Location: Fennell Campus: B-Wing 1st Floor: B103G
Description of Work: The contractor will be painting and installing baseboard. The electrician will be re-working the light switching.

Figure 1: Fennell Campus – B-Wing B103g
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
R-Wing – Change Rooms and Washroom AODA Accessories – FEB 09 to FEB 10
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Monday, February 9th, 2026 from 6:00 AM to 3:00 PM
Tuesday, February 10th, 2026 from 6:00 AM to 3:00 PM
Contractor: Britt Drywall
Location: Fennell Campus
R115, R116 and R117 – Women’s Change Rooms
R118, R119 and R120 – Men’s Change Rooms
R201b – Universal Washroom
Description of Work: The contractor will be installing washroom accessories to comply with AODA.
We apologize for any inconvenience this may cause and appreciate your understanding.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
G112 – Painting Walls – FEB 10
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Tuesday, February 10th, 2026 – 4:00 PM to 10:00 PM
Contractor: Footage Inc.
Location: Fennell Campus: G112
Description of Work: Footage Inc. will be on site on Wednesday, February 10th to paint walls in G112A.
For more information please contact:
Terry Walker – Lead Hand-Building Maintenance
Locksmith/Safe Technician
Email: terry.walker1 [at] mohawkcollege.ca (terry[dot]walker1[at]mohawkcollege[dot]ca)
Stoney Creek Campus (SC)
All Elevators - Scheduled Elevator Emergency Phone Line Updates – MAR 05 – 8:30 AM to 4:30 PM
Facility Services is providing notice of work that will be occurring at the Fennell and Stoney Creek Campus:
Thursday, March 5th, 2026 – 8:30 AM to 4:30 PM
Contractor: Schindler Elevator Corporation
Location: Fennell & Stoney Creek Campus - Elevators
Description of Work: Schindler Elevator technicians will be on site to reprogram the emergency phone lines for all elevators at the Fennell and Stoney Creek Campus. Each elevator will be taken out of service for up to one hour while its phone line is updated to the new emergency contact number.
Teams will work in sequence, with two crews on site to complete all elevators in one day. During this time, the elevator undergoing work will be temporarily unavailable; however, Schindler can provide access if required for students or staff. After reprogramming, each elevator will be functionally tested to ensure correct operation and call routing.
For more information please contact:
Paul Dalgleish – Manager, Buildings, Grounds and Housekeeping Operations
Email: paul.dalgleish [at] mohawkcollege.ca (paul[dot]dalgleish[at]mohawkcollege[dot]ca)
A140 & B102A – New Switchgear and Feeders – MAR 03, MAR 04, Mar 05 – 1:00 PM to 4:00 PM
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
- Tuesday, March 3rd, 2026 – 1:00 PM to 4:00 PM
- Wednesday, March 4th, 2026 – 7:00 AM to 4:00 PM
- Thursday, March 5th, 2026 – 7:00 AM to 4:00 PM
Contractor: Cahill Electric
Location: Stoney Creek Campus: B103a & A140 Electrical Rooms
Description of Work: Cahill Electric will be continuing the installation work for the new switchgear and feeders.
No impact to the operation of the College, all work will be contained within the two electrical rooms.
For further information – please contact:
Jim Davidson – Project Manager – Electrical & Construction
Email: james.davidson10 [at] mohawkcollege.ca (james[dot]davidson10[at]mohawkcollege[dot]ca)
E109E – Electrical Room Work – MAR 06 – 11:00 AM to 4:00 PM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Friday, March 6th, 2026 – 11:00 AM to 4:00 PM
Contractor: T.Lloyd Electric Ltd.
Location: Stoney Creek Campus: E109e Electrical Room
Description of Work: The contractor will be working in the main electrical room (E109e).
No power shutdowns, noise or dust is expected.
For further information – please contact:
Jim Davidson – Project Manager – Electrical & Construction
Email: james.davidson10 [at] mohawkcollege.ca (james[dot]davidson10[at]mohawkcollege[dot]ca)
E-Wing Electrical Conduit Installation - MAR 02 - MAR 05 - SCHEDULE OUTSIDE OF CLASS TIMES
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Monday, March 2nd, 2026 – 12:00 PM to 12:00 AM
Tuesday, March 3rd, 2026 – 4:00 PM to 12:00 AM
Wednesday, March 4th, 2026 – 4:00 PM to 12:00 AM
Thursday, March 5th, 2026 – 3:00 PM to 12:00 AM
**ALL WORK IS SCHEDULED TO AVOID ANY CLASSES IN ANY OF THE SHOPS.
Contractor: O’Keefe Electrical
Location: Stoney Creek Campus - E-Wing (Entire Building)
Description of Work: O’Keefe Electrical will be installing electrical conduit below the ceiling deck though all shops.
For further information – please contact:
Jim Davidson – Project Manager – Electrical & Construction
Email: james.davidson10 [at] mohawkcollege.ca (james[dot]davidson10[at]mohawkcollege[dot]ca)
G103 – Flooring Repair – MAR 02 – 11:00 AM to 4:00 PM
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Monday, March 2nd, 2026 – 11:00 AM to 4:00 PM
Contractor: Mattina Mechanical
Location: Stoney Creek Campus: Room G103 – Millwright Lab
Description of Work: Mattina Mechanical will be on site on Monday, March 2nd, to complete a flooring repair in Room G103 around the false floor.
The work is to take place from 11:00 AM to 4:00 PM.
Please note that the concrete may remain wet throughout the evening and overnight.
Please use caution when entering this area, it will be clearly marked with a safety cone.
For more information please contact:
Paul Dalgleish – Manager, Buildings, Grounds and Housekeeping Operations
Email: paul.dalgleish [at] mohawkcollege.ca (paul[dot]dalgleish[at]mohawkcollege[dot]ca)
A133, F-Wing and G-Wing – Washrooms Duress System – FEB 25 to FEB 27 – UPDATED NOTICE*
Facility Services is providing an updated notice of work that will be occurring at the Stoney Creek Campus.
Work is currently in progress today, and additional days of work have been scheduled as follows:
Updated Schedule: Wednesday, February 25th, 2026 to Friday, February 27th, 2026 – 8:00 AM to 5:00 PM
Revised Schedule: Tuesday, February 24th, 2026 – 8:00 AM to 5:00 PM
Original Schedule: Monday, February 23rd, 2026 – 8:00 AM to 5:00 PM
Contractor: O’Keefe Electrical
Location: Stoney Creek Campus
- A133 Universal Washroom
- F103 Women’s Washroom
- F105 Men’s Washroom
- G106 Universal Washroom (new)
- G108 Women’s Washroom (new)
- G112 Men’s Washroom (new)
Description of Work: O’Keefe Electrical will be upgrading/installing a Duress System in each washroom. The washrooms will be out of order during this time.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
B103A – Electrical Room Work – FEB 23 to FEB 25
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Monday, February 23rd, 2026 to Wednesday February 25th – 7:00 AM to 3:00 PM
Contractor: Cahill Electric Ltd.
Location: Stoney Creek Campus: B-Wing (B103A) & Parking Area Beside Shipping & Receiving
Description of Work: The contractor will be working in electrical room B103A.
As part of that work, a portable generator will be operating outside of the shipping and receiving area on Tuesday from 6:30am to 6:00pm. It will be positioned to respect clearance requirements from air intakes. Conductors will be routed from the portable generator and into B103a electrical room.
For further information – please contact:
Jim Davidson – Project Manager – Electrical & Construction
Email: james.davidson10 [at] mohawkcollege.ca (james[dot]davidson10[at]mohawkcollege[dot]ca)
E109A – Fire Suppression System – FEB 24
Facility Services is providing an updated notice of work that will be occurring at the Stoney Creek Campus:
Tuesday, February 24th, 2026 – 7:30 AM to 3:00 PM
Contractor: EPI Fire Protection Inc.
Location: Stoney Creek Campus – Room E109A
Description of Work: Removal of fire suppression system, devices and associated electrical components from the Paint Booth Room E109A.

Figure 1: Stoney Creek Campus - E109A Area of Work
For further information – please contact:
Natalie Fasan – Manager, Engineering Services & Projects
Email: natalie.fasan [at] mohawkcollege.ca (natalie[dot]fasan[at]mohawkcollege[dot]ca)
A122 – Wall Painting – FEB 27
Facility Services is providing notice of work that will be occurring at the Fennell Campus:
Friday, February 27th, 2026 – 6:00 PM to 10:00 PM
Contractor: Footage Inc.
Location: Stoney Creek Campus – Room A122
Description of Work: This work involves the preparation and repainting of the wall area where the former sound booth was removed in Room A122 at the Stoney Creek Library.
For further information – please contact:
Terry Walker – Locksmith – Team Lead – Building, Grounds & Housekeeping
Email: terry.walker1 [at] mohawkcollege.ca (terry[dot]walker1[at]mohawkcollege[dot]ca)
A133 and F-Wing – Washrooms Duress System – FEB 19 to FEB 20
Facility Services is providing an updated notice of work that will be occurring at the Stoney Creek Campus:
Revised Schedule: Thursday, February 19th, 2026 to Friday, February 20th, 2026 – 8:00 AM to 4:00 PM
Original Schedule: Friday, February 13th, 2026 – 8:00 AM to 4:00 PM
Contractor: O’Keefe Electrical
Location: Stoney Creek Campus
- A133 Universal Washroom
- F103 Women’s Washroom
- F105 Men’s Washroom
- G106 Universal Washroom (new)
- G108 Women’s Washroom (new)
- G112 Men’s Washroom (new)
Description of Work: O’Keefe Electrical will be upgrading/installing a Duress System in each washroom. The washrooms will be out of order during this time.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
A, B, C and D-Wing(s) – Exit Light Replacements – FEB 20
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Friday, February 20th, 2026 – 8:00 AM to 5:00 PM
Contractor: O’Keefe Electrical
Location: Stoney Creek Campus
- A-Wing Corridors, Stairwells both levels and A126a
- B-Wing Corridors, Stairwells both levels, B106 and B120
- C-Wing Corridors, C130 and C131
- D-Wing Corridors
Description of Work: O’Keefe Electrical will be replacing existing exit lights with new ones. They will work around class schedules.
All breakers impacted are labelled as Exit Lights.
Some moderate noise may occur at times, but will be kept to a minimum.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
E109A – Fire Suppression System – FEB 18
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
The work scheduled for Wednesday, February 18th, 2026 has been cancelled.
A new date and time will be communicated once rescheduled.
Contractor: EPI Fire Protection Inc.
Location: Stoney Creek Campus – Room E109A
Description of Work: Removal of fire suppression system, devices and associated electrical components from the Paint Booth Room E109A.

Figure 1: Stoney Creek Campus - E109A Area of Work
For further information – please contact:
Natalie Fasan – Manager, Engineering Services & Projects
Email: natalie.fasan [at] mohawkcollege.ca (natalie[dot]fasan[at]mohawkcollege[dot]ca)
A133 and F-Wing – Washrooms Duress System Installation – FEB 13
Facility Services is providing updated notice of work that will be occurring at the Stoney Creek Campus:
Friday, February 13th, 2026 – 8:00 AM to 4:00 PM
Contractor: O’Keefe Electrical
Location: Stoney Creek Campus
- A133 Universal Washroom
- F103 Women’s Washroom
- F105 Men’s Washroom
Description of Work: O’Keefe Electrical will be upgrading/installing a Duress System in each washroom. The washrooms will be out of order during this time.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
A, B, C and D-Wing(s) – Exit Light Replacements – FEB 13
Facility Services is providing an updated notice of work that will be occurring at the Stoney Creek Campus:
Friday, February 13th, 2026 – 8:00 AM to 5:00 PM
Contractor: O’Keefe Electrical
Location: Stoney Creek Campus
- A-Wing Corridors, Stairwells both levels and A126a
- B-Wing Corridors, Stairwells both levels, B106 and B120
- C-Wing Corridors, C130 and C131
- D-Wing Corridors
Description of Work: O’Keefe Electrical will be replacing existing exit lights with new ones. They will work around class schedules.
All breakers impacted are labelled as Exit Lights.
Some moderate noise may occur at times, but will be kept to a minimum.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
A140 & B103A – Electrical Room Work – FEB 09 to FEB 13
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Monday, February 9th, 2026 – Friday, February 13th, 2026 from 7:00 AM to 4:00 PM daily
Contractor: Cahill Electric Ltd.
Location: Stoney Creek Campus: A-Wing (A140), B-Wing (B103a)
Description of Work: The contractor will be working in A140 electrical room and B103a electrical room. No public-facing work is planned at this time.
There may be minor intermittent noise (drilling / hammering). No power interruptions are anticipated.
For further information – please contact:
Jim Davidson – Project Manager – Electrical & Construction
Email: james.davidson10 [at] mohawkcollege.ca (james[dot]davidson10[at]mohawkcollege[dot]ca)
A, B, C and D-Wing(s) – Exit Light Replacements – FEB 11
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Wednesday, February 11th, 2026 – 8:00 AM to 5:00 PM
Contractor: O’Keefe Electrical
Location: Stoney Creek Campus
- A-Wing Corridors, Stairwells both levels and A126a
- B-Wing Corridors, Stairwells both levels, B106 and B120
- C-Wing Corridors, C130 and C131
- D-Wing Corridors
Description of Work: O’Keefe Electrical will be replacing existing exit lights with new ones. They will work around class schedules.
All breakers impacted are labelled as Exit Lights. Some moderate noise may occur at times, but will be kept to a minimum.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
C-Wing – Corridor Painting – FEB 10
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Tuesday, February 10th, 2026 – 4:00 PM to 11:00 PM
Contractor: RV Painting
Location: Stoney Creek Campus: C-Wing Corridor between C115 to C120
Description of Work: The contractor will be painting corridor walls and doors/frames in C-Wing.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
B103A – Electrical Room Work – FEB 11
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Wednesday, February 11th, 2026 – 7:00 AM to 1:00 PM
Contractor: Demik Construction (sub-contactor to) Cahill Electric Ltd.
Location: Stoney Creek Campus: B-Wing (B103A) & Parking Area Beside Shipping & Receiving
Description of Work: The contractor will be working in the electrical room (Room B103A). No public-facing work is planned at this time.
A cement truck will be on-campus from approximately 7:30 AM till 12:00 PM. It will be parking in the access lane beside shipping and receiving.
For further information – please contact:
Jim Davidson – Project Manager – Electrical & Construction
Email: james.davidson10 [at] mohawkcollege.ca (james[dot]davidson10[at]mohawkcollege[dot]ca)
E-Wing – Full Building Power Shutdown – FEB 14
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Saturday, February 14th, 2025 – 7:00 AM to 3:30 PM
IMPORTANT: All power to the entire building will be OFF during this work. Please plan accordingly.
Contractor: T.Lloyd Electric Ltd. & Alectra Utilities
Location: Stoney Creek Campus: E-Wing - E109E & Outside of Building at Hydro Meter
Description of Work: The contractor (T.Lloyd Electric) and Alectra Utilities will be performing electrical renovations to the main hydro meter.
For further information – please contact:
Jim Davidson – Project Manager – Electrical & Construction
Email: james.davidson10 [at] mohawkcollege.ca (james[dot]davidson10[at]mohawkcollege[dot]ca)
C-Wing – Corridor Painting – FEB 09
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Monday, February 9th, 2026 – 4:00 PM to 11:00 PM
Contractor: RV Painting
Location: Stoney Creek Campus: C-Wing Corridor between C115 to C120
Description of Work: The contractor will be painting corridor walls and doors/frames in C-Wing.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
C-Wing and D-Wing – Corridor Painting – FEB 05
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
Thursday, February 5th, 2026 – 4:00 PM to 11:00 PM
Contractor: RV Painting
Location: Stoney Creek Campus:
- C-Wing Corridor between C115 to C120
- D-Wing Corridor between D101 to D104
Description of Work: The contractor will be painting corridor walls and doors/frames in C-Wing and D-Wing.
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
D-Wing – Pipe Insulation Replacement and Asbestos Abatement Work – FEB 05 & FEB 08
Facility Services is providing notice of work that will be occurring at the Stoney Creek Campus:
- Thursday, February 5th, 2026 – 4:00 PM to 11:00 PM
- Sunday, February 8th, 2026 – 7:00 AM to 3:30 PM
Security: Please let the contractor work later if they need to complete their work.
Contractor: McGowan Insulations
Location: Stoney Creek Campus: D-Wing between D102 and D112
Description of Work: The contractor will be replacing damaged pipe insulation, installing new pipe insulation, asbestos abatement of elbows and PVC wrapping piping.

Figure 1: Stoney Creek Campus – D-Wing Corridor
For further information – please contact:
Jeremy Dowling – Engineering Services Officer
Email: jeremy.dowling [at] mohawkcollege.ca (jeremy[dot]dowling[at]mohawkcollege[dot]ca)
Institute of Applied Health Sciences (IAHS)
Archived work notices are being prepared and will be available soon
Centre for Aviation Technology at Hamilton International Airport (HA)
Front and Rear Stairwells – Tile and Nosing Replacement – FEB 28
Facility Services is providing notice of work that will be occurring at the Centre for Aviation Technology at Hamilton International Airport (HA):
Saturday, February 28th, 2026 – 8:00 AM to 5:00 PM
Contractor: Mario's Tile & Interiors
Location: Centre for Aviation Technology at Hamilton International Airport (HA) – Front and Rear Stairwells
Description of Work: The contractor will replace damaged floor tile and stair nosing assemblies in both the front and rear stairwells.
For further information – please contact: